Monday, June 19, 2017

Sanitary Service Replacements On-Going. Water Main Replacement to Begin

Work Performed, June 12th to June 16th  
·         Sanitary sewer service replacements to homes on the south / east side of the street.  Sanitary sewer services on the north / west side of the street will not be replaced

Work Anticipated to be Performed, June 19th to June 23rd
·         Complete sanitary sewer service replacements
·         Water main connection at Maple Leaf Drive and Happy Hollow Road
·         Water main installation along Happy Hollow Road from Maple Leaf Drive working towards Willowbrook School

As work as started, there has definitely been an increase in the amount of construction traffic and inconveniences experienced by the residents along the roadway. Thank you for all your patience and understanding as you deal with the traffic delays, closure of the intersection of Maple Leaf Drive & Happy Hollow Road, water shut-downs (both planned and unplanned) and dirty roadways.

Monday, June 12, 2017

Construction to Start Mid-Week of June 12th

Construction will be starting the week of June 12th.

Work anticipated to be completed, June 12th to June 16th  
·         Mobilization of equipment
·         Delivery of materials
·         Tree removals / root pruning
·         Construction layout
·         Begin with sanitary sewer service replacements to those residents on the south side of Happy Hollow Road

The beginning of the week will see minimal activity as the contractor performs some preparation work prior to beginning. It is anticipated excavation work will begin on Wednesday.

Friday, June 2, 2017

2017 Construction to Begin June 12th

Now that the school year is coming to an end, preparations are being made to begin Phase II of the Happy Hollow Road Improvements.  The 2017 improvements will start where the 2016 Improvements left off just west of Willowbrook School and end at Maple Leaf Drive.

The same contractor, DiMeo Brothers, that performed the construction in 2016 will be performing the work in 2017.

Next week, you will begin to see some light activity including construction layout, utility locate markers, mobilization of equipment, and other miscellaneous tasks being performed.

Construction will start on Monday, June 12th with saw-cutting, mobilization of additional equipment, material deliveries, and start of underground utility construction.

The Village of Glenview will do everything possible to minimize the construction related inconveniences as much as possible, but as many residents lived through last year, many things are unavoidable.