Work anticipated to be
completed, June 12th to June 16th
·
Mobilization of equipment
·
Delivery of materials
·
Tree removals / root pruning
·
Construction layout
·
Begin with sanitary sewer service replacements
to those residents on the south side of Happy Hollow Road
The beginning of the week will see minimal activity as the
contractor performs some preparation work prior to beginning. It is anticipated
excavation work will begin on Wednesday.