Work Completed Last Week, July 25th to July 29th
·
Poured concrete driveway along Happy Hollow Road
·
Poured remaining concrete sidewalks and curb
& gutter along Happy Hollow Road
·
Performed rough grading of landscape along Happy
Hollow Road, Lawson Road, and Rebecca Lane
·
Graded and preparation work prior to paving
first 2 layers of asphalt pavement
·
Removal and pouring of 1st section of
concrete pavement along Greenwood Road at Happy Hollow Road and Rebecca Lane
·
Completed water service replacements along
Rebecca Lane
·
Made final connection to existing water main
along Rebecca Lane at Happy Hollow Road
·
Perform manhole adjustments along Rebecca Lane
Work Anticipated to be completed This week, August 1st
to August 5th
·
Install and grade topsoil in all areas disturbed
by construction activities along Happy Hollow Road, Rebecca Lane, and Lawson
Road
·
Remove and pour 2nd section of
concrete pavement along Greenwood Road at Happy Hollow Road and Rebecca Lane
·
Remove and pour concrete curb & gutter,
driveways, and sidewalks scheduled to be replaced along Rebecca Lane
·
Perform asphalt trench patching along Rebecca
Lane
·
Perform final testing of underground utilities
prior to installing asphalt surface
·
Adjust manholes within the pavement along Happy
Hollow Road
·
Perform walk-through with Village staff to
identify any areas that need to be addressed prior to asphalt surface paving
·
General Site Clean-Up
Work anticipated to be completed prior to start of school
year
·
Mill existing asphalt along Lawson Road and
Rebecca Lane.
·
Complete 3rd section of concrete
pavement removal and replacement along Greenwood Road at Happy Hollow Road and
Rebecca Lane
·
Paving final asphalt surface along Happy Hollow
Road, Rebecca Lane, and Lawson Road
·
Install pavement markings along Happy Hollow
Road, Greenwood Road, and Rebecca Lane
Thank you to all the residents along Happy Hollow Road that
were without driveway access for approximately 1.5 weeks. Your cooperation and
understanding is greatly appreciated and allowed for a significant amount of
work be completed in the most efficient manner possible. A major milestone was
reached last Friday, the first layers of asphalt pavement were installed. This
will provide a smooth driving surface as well as greatly reduce the amount of
dust along Happy Hollow Road.
Along Happy Hollow Road, there will be a lot of work getting
ready for the final asphalt surface layer to be paved prior to the start of the
school year. There will still be a significant amount of activity along Happy
Hollow Road, but likely not as many crews as previous weeks.
This week the contractor will begin installing and grading
topsoil as well as installing sod along Happy Hollow Road, Rebecca Lane, and
Lawson Road. The contractor will continue to water the sod once it is installed
until a healthy stand of grass is established.
Along Rebecca Lane, the underground utility improvements are
now completed!!! The contractor will begin the roadway improvements phase
of the project. This work will consist of removing and replacing concrete curb
& gutter, driveways, and sidewalks scheduled to be replaced or that were
damaged during construction and asphalt patching of the gravel trench where the
water main was installed. The entire roadway will have the existing asphalt
surface milled and repaved prior to the start of the school year.
The 2nd section of concrete pavement will be
removed and poured this week along Greenwood Road at the intersections of
Rebecca Lane and Happy Hollow Road. Thank you for all your cooperation and
patience as you travel through this intersection. Please use caution.
As you have seen, there has been a lot of work completed in
the past few months and the major construction is schedule to be completed
prior to the start of the fall school year, just 3 weeks away!!!
Thanks again for all your patience, understanding, and
cooperation!!!