Completed water service replacements
·
Made final connections to water main
·
Began Roadway excavation and installation of
gravel base.
Work Anticipated to be Performed, July 17th to
July 21st
·
Complete roadway excavation and installation of
gravel base
·
Prepare for concrete curb & gutter installation
·
Pour concrete curb & gutter
·
Pour concrete sidewalk and driveways
The underground utility work has been completed along the
project site including water main replacement, water service replacement,
sanitary sewer service replacement, and storm sewer improvements. The project
has now moved into the roadway reconstruction phase.
The roadway reconstruction phase includes removing the
existing concrete pavement and existing materials below the pavement to obtain
a stable base. The roadway will be constructed with a geotechnical fabric
between existing ground the gravel base, new 3-inch and 1 ¼-inch gravel base
with a total depth of approximately 12-inches, 9-inches of asphalt pavement,
and new concrete curb & gutter.
The roadway excavation and installation of geotechnical
fabric and gravel base are in the process of being constructed. The next step
will be to prepare for and pour the concrete curb & gutter followed to fine
grading the gravel base and paving the first layers of asphalt pavement.
Over the next 2 weeks, driveway access will be restricted to
all residents along the project site. Access will be restricted from the time
the string-line for the concrete curb & gutter is set to the paving of the
first layers of asphalt pavement. The exact dates for the beginning of driveway
restrictions is not yet determined, but it will likely start early the week of
July 17th with access restored by July 28th. The
Village of Glenview will provided notices to all residents affected by the
driveway restrictions. The notification will include dates and times to
have vehicles removed from the driveway, available parking options, and
anticipated timeframe access will be restored.
As you are aware, a significant rainfall event occurred
during the middle of the week. Unfortunately due to the stage of the
construction, a portion of the roadway was closed until the roadway could be
made passible the following day.
Thanks again for all your patience and understanding as you
deal with the extended driveway restriction in the coming weeks.