Completed concrete curb & gutter
installation
·
Completed pouring concrete driveways
·
Completed pouring concrete sidewalks
·
Rough graded landscape areas
·
Fine graded roadway in preparation for asphalt
paving.
·
Paved first layers of asphalt pavement.
Work Anticipated to be Performed, July 31st to
August 4th
·
Install and fine grade topsoil in areas of
landscape restoration
·
Adjust manholes within pavement
·
Perform final testing of underground
improvements
·
Perform walk-through of underground utilities
within roadway prior paving surface layer of asphalt
·
Pave surface layer of asphalt pavement
Now that the first layers of asphalt pavement are installed,
the amount of dust along the roadway is greatly reduced and a smooth driving
surface is provided. The construction project is nearing an end with the last
major items of work being asphalt surface paving and landscape restorations.
The contractor is on schedule to have the project completed, with the exception
of sod installation, prior to the start of the school year.
Next week, the contractor will begin installing and grading
topsoil in areas requiring landscape restoration. However, sod will not be
installed until the September/October timeframe to allow for more favorable
growing conditions.
Thank you to all the residents along the construction site
that were without driveway access for the past 2 weeks. Your patience and
understanding is greatly appreciated. Driveway access will be restored as
anticipated by Friday, July 28th.