Poured concrete sidewalks in locations
previously removed.
·
Completed water service replacements along Happy
Hollow Road
·
Completed water service replacements along
Lawson Road
·
Made connection to existing water service to
Willowbrook School
·
Made connection between existing water main and
newly installed water main at Happy Hollow Road and Phase I Limits
·
Make connection between existing water main and
newly installed water main along Lawson Road
·
Saw-cutting existing pavement in location of
proposed water main along Rebecca Lane
·
Made connection between existing water main and
new water main at Rebecca Lane and Greenwood Road
·
Began installation of new water main along
Rebecca Lane
·
Began roadway excavation and installation of
aggregate base course along Happy Hollow Road.
Work Anticipated to be completed Next week, July 18th
to July 22nd
·
Complete water main installation along Rebecca
Lane
·
Perform necessary testing and receive approval
to place newly installed water main along Rebecca Lane into service
·
Roadway patching along Lawson Road
·
Continue with roadway excavation and
installation of aggregate base course along Happy Hollow Road
·
Depending on work progress, install string line
and grading in preparation for concrete curb & gutter installation along Happy
Hollow Road
The contractor is anticipating to complete the water main
installation along Rebecca Lane next week and begin performing the required
tests and receiving the necessary approvals to place the new water main into
service. Water service replacements along Rebecca Lane are anticipated to begin
the week of July 25th.
The roadway improvements along Happy Hollow Road with
excavation of the existing pavement and installation of aggregate base course
has started and will continue through next week. During the roadway excavation
phase, the driveways within the daily work area will be restricted. The
contractor will provide notice as to which day your driveway access will be
restricted. We request you have your vehicles out of your driveways and garages
by 7:00 AM the day work adjacent to your home is expected to be completed.
Access will be restored by 5:00 PM or early depending on work progress.
Depending on work progress, the contractor will begin
installing a string line and grading the under the proposed concrete curb &
gutter in preparation for pouring new concrete curb & gutter. Once the
string line is installed and concrete work begins, residents will be restricted
from their driveways for an extended period of time, approximately 1 ½ weeks.
This extended period of time is to allow for the contractor to complete
concrete curb & gutter, sidewalk, and driveway installation; allowing
proper time for the concrete to cure; grading and installing additional
aggregate base course on the roadway; and paving the first layers of asphalt
pavement. As the schedule is finalized, residents will be notified regarding
the timing of this work to be performed and when access to your driveways is
expected to be restored.
There is a lot of construction activity along Happy Hollow
Road, Lawson Road, and Rebecca Lane as the contractor continues to meet the
construction schedule and get as much work as possible completed prior to the
start of school. Please you caution as you walk and travel through the
construction zones.
Thank you again for your patience and understanding as you
have been dealing with water main shut-downs, travel delays due to work along
Greenwood Road and neighboring streets, dusty conditions, and driveway
restrictions. We understand the significant inconveniences these cause to your
daily lives and are committed to limiting them to the greatest extent possible.