·
Performed final testing of underground
utilities.
·
Completed sod installation along Happy Hollow
Road, Rebecca Lane, and Lawson Road
·
Removed and poured 3rd (and final) section
of concrete pavement along Greenwood Road at Happy Hollow Road and Rebecca Lane
·
Milled 2-inches of the existing asphalt surface
along Rebecca Lane, Lawson Road, and a few other miscellaneous areas.
·
Abandoned old water main.
·
Paved final lift of asphalt pavement along the
entire project site.
·
General Site Clean-Up
Work Anticipated to be completed This week, August 15th
to 19th
·
Perform walk-through with Village staff to
identify any areas that need to be addressed prior to project close-out.
·
Complete minor items remaining to be repaired
·
Open
all lanes along Greenwood Road to traffic
·
Install
pavement markings along project site.
Sod installation is now completed along the entire project
site. The contractor will continue to water the sod until a healthy stand of
grass is established.
Now that the sod installation is completed in front of your
homes, you may contact your irrigation contractor if your system was damaged
during construction operations. Your irrigation contractor should be able to
easily lift up the newly installed sod and make any needed repairs, then re-install
the sod. The Village does not reimburse or pay for private improvements within
the public right-of-way that were damaged during the construction project.
With the final layer of asphalt pavement installed, the
major construction operations are completed. There are only a few minor items
of work to be completed on-site prior to the start of the school year!!!