·
Completed water main installation along Rebecca
Lane
·
Started performing necessary testing to place
newly installed water main along Rebecca Lane into service
·
Completed storm sewer improvements along Rebecca
Lane
·
Performed excavations in preparation for water
service replacement along Rebecca Lane
·
Trench patching along Lawson Road
·
Install and grade topsoil along Lawson Road
·
Complete roadway excavation and installation of
aggregate base course along Happy Hollow Road
·
Installed string line along Happy Hollow Road in
preparation for concrete curb & gutter installation along Happy Hollow Road
·
Graded aggregate base under proposed concrete
curb & gutter in preparation for pouring along Happy Hollow Road
·
Poured concrete curb & gutter on Happy
Hollow Road
·
Graded and prepared for pouring concrete
driveways along Happy Hollow Road
Work Anticipated to be completed Next week, July 25th
to July 29th
·
Pour concrete driveways along Happy Hollow Road
·
Pour remaining concrete curb & gutter along
Happy Hollow Road
·
Pour remaining concrete sidewalks along Happy
Hollow Road
·
Rough grading of landscape behind curb &
gutter along Happy Hollow Road
·
Grading of roadway in preparation for asphalt
pavement along Happy Hollow Road
·
Pave first layers of asphalt pavement along Happy
Hollow Road, scheduled for Friday, July 29th
·
Removal of a portion of concrete pavement along
Greenwood Road at Happy Hollow Road and Rebecca Lane
·
Pouring concrete pavement along Greenwood Road
at Happy Hollow Road and Rebecca Lane
·
Water Service Replacements along Rebecca Lane
·
Depending on work progress and scheduling,
milling existing asphalt along Lawson Road and Rebecca Lane.
Once the water service replacements along Rebecca Lane are
completed, the contractor will begin the roadway improvements phase of the
project on Rebecca Lane. The roadway improvements will include patching the
excavated area, milling the top surface off the existing pavement, making spot
concrete curb & gutter and sidewalk repairs, and installing a new asphalt
surface layer. The roadway improvements are not as significant as those
occurring along Happy Hollow Road, where the entire roadway is being
reconstructed.
Happy Hollow has had a lot of activity over the past week in
preparation for the concrete curb & gutter installation. It is anticipated
all the concrete curb & gutter, sidewalk, and driveway work will be
completed by the middle of next week. The only exception is the driveway
entrance to Willowbrook School which will be completed after access to all
other driveways is restored.
If all goes as planned and there are no significant delays in production or due to weather, the first layers of asphalt pavement will be installed along Happy Hollow Road by the end of next week. Once the first layers of asphalt pavement are installed, the amount of dust will be greatly reduced and driveway access will be restored. We are extremely grateful for the patience and understanding from all the residents that live along Happy Hollow Road. These residents will be without driveway access for over a week to allow for the concrete installation and curing, as well as the roadway paving to be performed in the most efficient manner possible. THANK YOU!!!!
Also next week the contractor will begin concrete pavement
replacement along Greenwood Road at the intersections of Happy Hollow Road and
Rebecca Lane. This work will be performed in phases to allow for one lane of
traffic along Greenwood Road. However, we expect some travel delays as both
lanes of traffic will need to access a single lane. Please use caution while
traveling along Greenwood Road. Due to performing the work in phases, it will
take 2-3 weeks to complete the concrete pavement repairs within the
intersections. This will allow for proper concrete curing prior to opening the
lanes to traffic and beginning the next phase of the intersection.
Thank you again to all the residents within the neighborhood
for your patience and understanding. The project is moving along smoothly and
ahead of schedule due to your cooperation. Getting the first layer of asphalt
pavement installed along Happy Hollow Road will be a major project milestone
and will greatly reduce some of the significant travel delays and dust along
Happy Hollow Road. Please use caution and be patient traveling along Greenwood
Road for the next few weeks as the intersection work will be on-going.