Friday, June 24, 2016

Water Main Replacement Continues. Storm Sewer Improvements to Begin

Work Completed Last Week, June 20th to June 24th
·         Continued with water main replacement along Happy Hollow Road
·         Installed new water main through Willowbrook School property via directionally drilled methods.

Work Anticipated to be completed Next week, June 27th to July 1st
·         Complete water main replacement along Happy Hollow Road to Phase I limits
·         Complete water main replacement along Lawson Road
·         Begin performing required tests and receiving necessary approvals prior to placing the new water main into service
·         Perform storm sewer replacement and improvements along Happy Hollow Road

The contractor will bring a second crew in next week to complete the water main installation along Lawson Road. If all goes as anticipated, a majority of the water main installation will be completed by the end of next week.

Once the new water main is installed, the contractor will begin performing tests and receiving the required approvals prior to placing the new water main into service and replacing the water services to individual homes. It is anticipated water service replacements will begin soon after the July 4th Holiday.

Thanks again for all your patience and understanding as you deal with the dust and inconveniences associated with living in and around a construction area.

 

Friday, June 17, 2016

Construction Started!!! Sanitary Sewer Service Replacements Completed. Water Main Replacement to Begin

Work Completed Last Week, June 13th to June 17th  
·         Completed sanitary sewer replacements along Happy Hollow Road under the existing pavement.
·         Saw-cutting existing pavement along the project site.
·         Tree trimming along the project site.
·         Tree removal along Lawson Road
·         Continued to mobilize equipment and materials to the site
·         Excavate boring pit in anticipation of direction drilling the new water main through the Willowbrook School property.

Work Anticipated to be completed Next week, June 20th to June 24th  
·         Begin water main replacement along Happy Hollow Road starting at Greenwood Road and working west.
·         Directionally drill new water main through Willowbrook School property

The dust has been a concern over the past week. The contractor is committed to watering and sweeping the roadway on a consistent basis to reduce the amount of dust to the greatest extent possible. Unfortunately, the amount of dust will only increase as the underground utility installation continues by excavating through the existing pavement.

As the water main installation begins, there will scheduled water main shut-downs that will affect water service to each home. Affected residents will be notified via a door hanger the day prior to a scheduled water main shut down, please be on the look-out for these notifications.

Major construction as started!!!  Thank you for all your patience and understanding as the construction as started. Please understand we fully understand the significant inconveniences that you are experienced living in a construction area. We will do everything possible to minimize those inconveniences to the greatest extent possible.

 

 

Friday, June 10, 2016

Construction to Begin

Work Completed Last Week, June 6th to June 10th
·         Resident preconstruction meeting conducted on Monday, June 6th
·         Internal televising of underground utilities
·         Underground utility locates by utility owners
·         Construction layout
·         Traffic control devices delivered to site
·         Mobilization of construction equipment and materials

 Work Anticipated to be completed Next week, June 13th to June 17th
·         Sanitary sewer service replacement under Happy Hollow Road pavement
·         Tree trimming and/or removal of those trees scheduled to be removed and have been previously posted indicating they will be removed
·         Saw-cutting the existing roadway in the locations of the proposed underground utility improvements

Thank you to all the residents that attended the Preconstruction Meeting on Monday night. It was an informative meeting with significant resident feedback. We were able to explain what the residents can expect during the construction process.

The major construction will begin on Monday, June 13th, starting with the sanitary sewer service replacements. There will be a significant amount of heavy equipment and materials along the entire project site. Driving along Happy Hollow Road will be increasingly more difficult due to the contractor digging across the street. Please drive carefully and consider using alternates routes if at all possible.

The Village understands the significant inconveniences experienced by residents that live along a construction work area. We will do everything possible to limit these inconveniences to the greatest extent possible. We thank you for your patience and understanding for the duration of the project.